Most Popular

Most Viewed
Most Commented
News
"Most Popular" tools sponsored by:
Recent Articles

Recent Articles By Peter Byrne

  • Politically Inspired: Fiction for Our Time
    A gemlike collection of 30 short stories, ranging from comic and satirical to ironic and sad
  • Surprise!
    If you think S.F. is ready for a terrorist attack – even two years-plus after 9/11 – think again
  • Capital Rap
    From revolutionary rapper to stockbroker to rapper again -- the long, strange trip of Paris, aka Oscar Jackson Jr.
  • Gaffing Gavin
    In which we head into the Tenderloin on a secret nocturnal mission
  • Molotov Mouths: Explosive New Writing
    A verbally incendiary band of activist-poets' fresh, passionate, revolutionary collection

National Features

" In mid-1999, Tutor-Saliba charged nearly $5 million for fixing two concrete floors that were not poured level. In a change order, SFO Associates said the mistake may have happened because measurements were "inexact." They also expressed concern about the design of the structural steel beams below the slabs. The airport says that it is investigating who is at fault for the floor problem.

" Tutor-Saliba charged $647,000 to fill a series of roof-support column frames with concrete. According to an airport spokesperson, "Either the architects or engineers forgot to indicate that the [wood] column frames needed to be filled with concrete." Apparently, the original plans called for constructing empty frames. It is odd that such a large oversight could make it past teams of architects, engineers, construction managers, and the contractors who methodically scrutinize plans to calculate their bids. In an interview last week, Ron Tutor said that it is not the contractor's responsibility to identify errors in the bid specifications. No one has been penalized for the oversight.

" Tens of thousands of dollars were spent to rebuild steel and concrete openings for escalators. The slots for the escalators were built before the airport decided what size moving stairs would be bought. A similar situation occurred when the airport spent $1 million to retrofit steel beams that support the terminal floor: The beams were set in place before the size of pipes fitting under the floor were known.

And that's just a few of the more than 400 change orders Tutor-Saliba has submitted for its airport work. Tracking those change orders, however, is no easy task. In response to an SF Weekly public records request, an airport lawyer said that many change orders could not be found -- even though the airport has paid construction managers several million dollars for "document control" related to the master plan.

The change orders the airport did make public, however, raise numerous questions about oversight of costs at the airport. In August 1997, Tutor-Saliba charged the airport $240,000 for a furnished triple-wide office trailer for use by SFO Associates, the construction management firm that oversees Tutor-Saliba's work. A representative of GE Capital Modular Space, which manufactures construction office trailers in the Bay Area, says his firm charges $97,200 for a similar brand-new trailer, and rents such models for $1,731 a month.

As part of its contract to build the terminal, Tutor-Saliba also billed the airport $330,000 to build indoor office space for the construction management consultants. It even billed the airport $1,000 a month for cleaning these offices.

In October 1998, a joint venture known as Myers/Condon Johnson, which is building new freeway ramps to serve the airport, received a change order listing more than $2 million for "additional unidentified work." When asked about this change order, airport staffers said that use of the word "'unidentified' may be misleading. It is used in the context of scope that could not be fully defined during design and is therefore 'unidentified' on the contract documents." In other words, the airport acknowledged, it signed a contract that included provisions requiring the airport to pay for undefined amounts and types of work.

Perhaps the most troubling change orders are those relating to many millions of dollars spent to revise the positions of structural, mechanical, electrical, and plumbing systems that were already in place at the new terminal. As structural steel beams were cut and rewelded to fix mistakes, or to expand concession space, or to accommodate special changes requested by the airlines, the placement of environmental support sys-tems behind ceilings and walls was shifted, adding tremendous cost to the project. In effect, significant portions of the terminal were built twice.

And then there is the mother of all change orders: the change order to write change orders. Tutor-Saliba billed $428,000 to pay for staff to write and process the blizzard of change orders Tutor-Saliba eventually submitted. Tutor says that he "does not get rich off of change orders," which, he contends, include only a 5 percent profit margin for his firm. But he declined to reveal the amount his company will profit from its SFO contracts.

One of the bigger wellsprings of SFO change orders is requests from the airlines that use the airport's terminals, led by United Airlines, which has one of its hubs at SFO. The airlines have a contract with the airport that limits the amount of construction costs that can be passed through to them. Through its position on the airport advisory committee, the Airline Liaison Office, which represents the airlines' interests, has considerable influence over the master plan. During the international terminal project, this combination of contractual limits and administrative influence has led to a situation in which millions of dollars of design and construction work was apparently done more than once.

Long after the construction contracts for the international terminal complex were let, the airlines, led by United, decided they wanted several exclusive lounges for use by first-class passengers. The Airport Commission approved these dramatic, costly changes, which include a $2.2 million lounge added to one boarding wing of the terminal. A similar lounge is in the works for the terminal's other boarding wing. All in all, there will be 14 lounges and clubhouses scattered about the new terminal.

Neither United Airlines nor SFO's Airline Liaison Office returned telephone calls seeking comment for this article. But, according to change order documents, inserting United Airlines' lounge required structural changes to the building's steel frames, including the addition of elevators and escalators, the removal of walls, and the relocation of electrical conduits, water and sewage pipes, ventilation ducts, and fire control systems. It took years to bend the buildings around the airlines' new clubhouses. Overall, the airport attributes $91 million in change orders to direct requests from the airlines and concessionaires.

There are other seemingly less than vital odd items larded into master plan change orders approved by the Airport Commission. When travelers are not eating fast food, or buying liquor in duty-free shops, SFO provides a scattering of mini-art museums for viewing pleasure. Over the years, these temporary exhibits have ranged in content from ancient boating artifacts to a retrospective of post-World War II children's lunch pail art. Now, however, the new international terminal will be home to a permanent, $4 million Aviation Archive, Library, and Museum, housed in a 6,000-square-foot replica of SFO's first terminal, built in 1937.

SF Weekly Insiders

  • Local food, music and news blasts
  • Free Stuff
Warfield